Under the Carbon Border Adjustment Mechanism (CBAM), EU importers can only declare an installation's actual emissions once an accredited verifier has checked them. Verification is the step that turns an installation's emissions report into data its EU customers can use.

Who carries out CBAM verification?

An accredited CBAM verifier, appointed by the installation's operator. National accreditation bodies in the EU accredit CBAM verifiers, and verifiers based outside the EU can apply to any of those bodies. The Commission publishes a list of the national accreditation bodies that accredit CBAM verifiers.

What does the verifier check?

The verifier checks the installation's emissions report against its monitoring plan. They assess whether the plan meets the requirements, whether the installation followed it during the year, and whether the reported emissions are free from material misstatements.

Verifiers work to a standard of reasonable assurance, a high but not absolute level of certainty. The materiality threshold is 5% of the specific embedded emissions of the goods concerned. That threshold decides whether the report can pass. It isn't a margin of error, and the verifier expects the operator to correct, in principle, every misstatement it finds.

What happens during verification?

Verification follows a set sequence.

  1. Planning. The verifier reviews the monitoring plan and the installation's documents, assesses where errors are most likely, and plans the verification around those risks.
  2. Site visit. The verifier visits the installation to check its processes, emission sources, meters, and records against the monitoring plan.
  3. Data checks. The verifier traces the figures in the emissions report back to their source data and checks the calculations.
  4. Findings. The verifier tells the operator about any misstatements or gaps it finds, and the operator corrects them in the monitoring plan and emissions report.
  5. Review and report. A reviewer who wasn't part of the verification team checks the work, and the verifier issues its verification report.

Isometric's experts prepare installations for each of these steps.

Is a site visit required?

Yes, for an installation's first verification. The verifier must visit the installation in person. In later years, the verifier can sometimes replace the physical visit with a virtual one, or waive it, if its risk analysis shows the verification won't be less reliable as a result.

What happens if the verifier finds problems?

The operator corrects them, and the verifier checks the corrections. If problems remain that are large enough to be material, the verifier issues an unsatisfactory opinion. The installation's EU customers can't then use its actual emissions and have to declare default values instead.

What is the verification report?

The verification report records the verifier's opinion on whether the emissions report is satisfactory, along with details of the installation, the verification team, the site visit, and any findings. The verifier prepares it using the Commission's electronic template in the CBAM Registry.

Once verification is complete, the operator shares the verified emissions data and the verification report with its EU customers. They use them in their annual CBAM declarations.

When does verification take place?

After the reporting year ends, since the verifier needs the full year's data. Verifiers can issue reports for 2026 from January 2027. Importers must submit their declarations for 2026 imports by September 30, 2027, so installations should plan the site visit and allow time to correct any findings well before then.

The Commission's CBAM verification guidance sets out the full requirements.

How Isometric helps

Ready for CBAM is advisory and software from Isometric for installation operators outside the EU. It brings together Isometric's carbon accounting experts and AI agents to turn raw production data into a monitoring plan and emissions report that's ready for verification. Isometric's experts also support installations through the audit and with any findings, but take no part in the verifier's decision.

Get ready for CBAM

Ready to certify?

Fast, accurate certification for project developers and buyers.

Backed by ICE, owner of the New York Stock Exchange
CERTIFICATE